2019/2020 FINANCIAL YEAR PROJECTS

Kipkelion East Sub County

- All Projects-
Go back

Project Department Status Budget(Kshs) Ward
Kaptaragon Borehole Water Project Water, Environment, Energy and Natural Resources Completed 1,613,832.88 Chepseon Feedback
Chepseon Polytechnic Borehole Water, Environment, Energy and Natural Resources Completed 1,624,649.60 Chepseon Feedback
Kaplelachbei water project Water, Environment, Energy and Natural Resources Completed 1,494,486.00 Chepseon Feedback
Chilchilla Pan Rehabilitation Water, Environment, Energy and Natural Resources Completed 1,386,788.17 Chepseon Feedback
Chepsain Water Project Water, Environment, Energy and Natural Resources Completed 1,893,521.36 Chepseon Feedback
Chepseon Water projects (Tugunon Water project) Water, Environment, Energy and Natural Resources Completed 1,138,236.54 Chepseon Feedback
Londiani water supply Water, Environment, Energy and Natural Resources Completed 1,375,551.20 Kedowa/Kimugul Feedback
Rehabilitation of Tulwapsigis Pan Water, Environment, Energy and Natural Resources Completed 1,725,152.00 Kedowa/Kimugul Feedback
Kapkeri Water Project Water, Environment, Energy and Natural Resources Completed 1,129,751.40 Kedowa/Kimugul Feedback
Katet Borehole Water project Water, Environment, Energy and Natural Resources Completed 1,453,619.20 Londiani Feedback
Kiptangit Water project Phase 1 Water, Environment, Energy and Natural Resources Completed 1,009,391.08 Londiani Feedback
Rouitne Maintenance of 938- Leberer-Kamachungwa Road Public Works, Roads and Transport Completed 2,397,635.00 Chepseon Feedback
Kiptangit Water Project Phase II Water, Environment, Energy and Natural Resources Completed 1,141,788.00 Londiani Feedback
Routine Maintenance of Kamarus – Annex Road Public Works, Roads and Transport Completed 2,495,763.00 Chepseon Feedback
Masaita Borehole Water Projects Water, Environment, Energy and Natural Resources Completed 871,160.00 Londiani Feedback
Routine Maintenance of Kosovo – Sailo Road Public Works, Roads and Transport Completed 2,952,891.00 Chepseon Feedback
Barotion Water Project Water, Environment, Energy and Natural Resources Completed 1,559,712.80 Londiani Feedback
Routine Maintenance of Kap Zakayo-Simotwet Road Public Works, Roads and Transport Completed 1,805,412.00 Chepseon Feedback
Kamwingi II Water Project Water, Environment, Energy and Natural Resources Completed 2,621,429.48 Tendeno/Sorget Feedback
Routine Maintenance of Off B1 -ngatumek pry, and Kapchumo Road Public Works, Roads and Transport Completed 3,152,100.00 Kedowa/Kimugul Feedback
Benditai Water Project. Water, Environment, Energy and Natural Resources Completed 2,613,029.92 Tendeno/Sorget Feedback
Routine Maintenance of Off Kedowa Pry. - Testai - Kabisoi Road Public Works, Roads and Transport Completed 1,924,548.00 Kedowa/Kimugul Feedback
Kivuno Borehole Water Project Water, Environment, Energy and Natural Resources Completed 2,114,104.64 Tendeno/Sorget Feedback
Routine Maintenance of Cherote-Lelsotet Road Public Works, Roads and Transport Completed 2,835,556.00 Kedowa/Kimugul Feedback
Jagoror Water Project Water, Environment, Energy and Natural Resources Completed 1,618,340.32 Tendeno/Sorget Feedback
Routine Maintenance of Off B1-Kapchumo Road Public Works, Roads and Transport Completed 1,639,906.00 Kedowa/Kimugul Feedback
Kiploikyi water project- solar Water, Environment, Energy and Natural Resources Completed 2,069,115.20 Tendeno/Sorget Feedback
Routine Maintenance of Arap Chepyoset-Job-Southrift Road Public Works, Roads and Transport Completed 1,573,967.00 Londiani Feedback
A Routine Maintenance of Arap Kogo-Lolongbei Road and Jagoror Quarry Road Public Works, Roads and Transport Completed 1,338,591.00 Londiani Feedback
Routine Maintenance of United Soy-Kiplangat Road Public Works, Roads and Transport Completed 2,033,584.00 Londiani Feedback
Routine Maintenance of Cheres-Orwasa Road Public Works, Roads and Transport Completed 1,930,816.00 Londiani Feedback
Routine Maintenance of OffD314 - Benjamin Road Public Works, Roads and Transport Completed N/A Tendeno/Sorget Feedback
Routine Maintenance of Off E254-Kamuingi-Kichagi-Gwitu Road Public Works, Roads and Transport Completed 2,540,493.00 Tendeno/Sorget Feedback
Routine Maintenance of Cheborge Junction-Center One Forest Road Public Works, Roads and Transport Completed 2,141,488.00 Tendeno/Sorget Feedback
Routine Maintenance of Kapilot -Sorget Road Public Works, Roads and Transport Completed 2,929,766.00 Tendeno/Sorget Feedback
Masaita Education, Youth Affairs, Sports, Culture and Social Services Completed 1,503,401.20 Londiani Feedback
Jambo Education, Youth Affairs, Sports, Culture and Social Services Completed 1,098,788.00 Tendeno/Sorget Feedback
Londiani farmers Education, Youth Affairs, Sports, Culture and Social Services Completed 1,465,692.48 Londiani Feedback
Kabarak Education, Youth Affairs, Sports, Culture and Social Services Completed 3,676,037.48 Londiani Feedback
Chepcholiet Education, Youth Affairs, Sports, Culture and Social Services Completed 3,922,478.60 Chepseon Feedback
Cheboror Education, Youth Affairs, Sports, Culture and Social Services Completed 2,871,238.20 Chepseon Feedback
Irerma Education, Youth Affairs, Sports, Culture and Social Services Completed 5,600,000.00 Kedowa/Kimugul Feedback
Tiriita Education, Youth Affairs, Sports, Culture and Social Services Completed 4,480,000.00 Kedowa/Kimugul Feedback
Ngatumek Education, Youth Affairs, Sports, Culture and Social Services Completed 3,360,000.00 Kedowa/Kimugul Feedback
Tumaini Education, Youth Affairs, Sports, Culture and Social Services Completed 2,240,000.00 Tendeno/Sorget Feedback
Mugumoine Education, Youth Affairs, Sports, Culture and Social Services Completed 2,240,000.00 Tendeno/Sorget Feedback
Kamuogo Education, Youth Affairs, Sports, Culture and Social Services Completed 2,240,000.00 Tendeno/Sorget Feedback
Kapkondoo ECDE Education, Youth Affairs, Sports, Culture and Social Services Completed 1,680,000.00 Londiani Feedback
Chepkongony ECDE Education, Youth Affairs, Sports, Culture and Social Services Completed 2,240,000.00 Kedowa/Kimugul Feedback
Tulwap Kiplekwa ECDE Education, Youth Affairs, Sports, Culture and Social Services Completed 2,912,000.00 Kedowa/Kimugul Feedback
Ngatumek ECDE Education, Youth Affairs, Sports, Culture and Social Services Completed 1,680,000.00 Kedowa/Kimugul Feedback
Sailo ECDE Education, Youth Affairs, Sports, Culture and Social Services Completed 1,120,000.00 Chepseon Feedback
Chepchabai ECDE Education, Youth Affairs, Sports, Culture and Social Services Completed 2,240,000.00 Chepseon Feedback
Jambo ECDE Education, Youth Affairs, Sports, Culture and Social Services Completed 896,000.00 Tendeno/Sorget Feedback
Construction of a Classroom at Leberer ECDE Centre Education, Youth Affairs, Sports, Culture and Social Services Completed 2,240,000.00 Chepseon Feedback
Construction of an Administration Block and Library at 938 VTC Education, Youth Affairs, Sports, Culture and Social Services Completed 2,912,000.00 Chepseon Feedback
Construction of pit latrine at Chesinende ECDE Centre Education, Youth Affairs, Sports, Culture and Social Services Completed 672,000.00 Chepseon Feedback
Construction of pit latrine at Kapchemusian ECDE Centre Education, Youth Affairs, Sports, Culture and Social Services Completed 1,120,000.00 Chepseon Feedback
Construction of pit latrine at Kaptaragon ECDE Centre Education, Youth Affairs, Sports, Culture and Social Services Completed 448,000.00 Chepseon Feedback
Construction of pit latrine at Lamaiyat ECDE Centre Education, Youth Affairs, Sports, Culture and Social Services Completed 2,240,000.00 Chepseon Feedback
Construction of a pit latrine at Kimasian ECDE Centre Education, Youth Affairs, Sports, Culture and Social Services Completed N/A Kedowa/Kimugul Feedback
Construction of 2 Classrooms at Londiani Vocational Training Centre Education, Youth Affairs, Sports, Culture and Social Services Completed 672,000.00 Londiani Feedback
Construction of ECDE classroom at Kapkwen ECDE Centre Education, Youth Affairs, Sports, Culture and Social Services Completed 3,136,000.00 Londiani Feedback
Construction of a classroom at Kapsinendet ECDE centre Education, Youth Affairs, Sports, Culture and Social Services Completed 560,000.00 Londiani Feedback
Construction of ECDE classroom at Jambo ECDE Centre Education, Youth Affairs, Sports, Culture and Social Services Completed 1,680,000.00 Tendeno/Sorget Feedback
Construction of a classroom at Kamuogo ECDE Centre Education, Youth Affairs, Sports, Culture and Social Services Completed 1,120,000.00 Tendeno/Sorget Feedback
Completion and Renovation of ECDE classrooms at Chebaibai and Kamaua ECDE Centres Education, Youth Affairs, Sports, Culture and Social Services Completed 1,120,000.00 Tendeno/Sorget Feedback
Construction of a 3 door pit latrine at Sorget ECDE Centre Education, Youth Affairs, Sports, Culture and Social Services Completed 1,680,000.00 Tendeno/Sorget Feedback
Kericho Forest Dispensary Health Services Completed 1,988,890.00 Chepseon Feedback
Construction of Kimaut-Karap Bangoror Culvert Public Works, Roads and Transport Completed 3,500,004.20 Londiani Feedback
Kamachungwa Dispensary Health Services Completed 2,014,036.00 Chepseon Feedback
Construction of Lelsotet-Saw mill Pipe Culverts Public Works, Roads and Transport Completed 1,688,640.00 Londiani Feedback
Kiletien Dispensary Health Services Completed 2,680,560.00 Chepseon Feedback
Construction of Kap Jackson-Anderea Pipe Culverts Public Works, Roads and Transport Completed 1,430,494.50 Londiani Feedback
Kiletien Dispensary Health Services Completed 3,242,411.00 Chepseon Feedback
Construction of Kapkondoo-Binam pipe culvert Public Works, Roads and Transport Completed 1,989,836.00 Londiani Feedback
Chepcholiet Dispensary phase 2 Health Services Completed 1,271,443.00 Chepseon Feedback
Construction of drainage Structures at Barotion Road Public Works, Roads and Transport Completed 1,945,686.56 Londiani Feedback
Proposed Construction of toilets and Final Paint Works at Kiletien Dispensary Health Services Completed 1,296,274.00 Chepseon Feedback
Construction of Jagoror Bridge and Maintenance of the abutments Public Works, Roads and Transport Completed 1,551,765.17 Londiani Feedback
Proposed Completion of OPD at Kamachungwa Dispensary Health Services Completed 2,003,440.00 Chepseon Feedback
Construction of Lelsotet- Sawmill Pipe Culverts Public Works, Roads and Transport Completed 1,144,000.00 Londiani Feedback
Proposed completion of OPD, construction of two door pit latrine and installation of 10, 000L water tank at Chepcholiet Dispensary Health Services Completed 3,904,800.00 Chepseon Feedback
Construction of Murazoi Box Culvert Public Works, Roads and Transport Completed 1,792,349.04 Chepseon Feedback
Proposed completion of maternity room at Momoniot Dispensary Health Services Completed 2,700,200.00 Chepseon Feedback
Construction of Arap Soi Box Culvert Public Works, Roads and Transport Completed 1,450,000.00 Kedowa/Kimugul Feedback
Proposed completion of OPD, extension of a verandah and waiting bay, supply and installation of 5000 liters water tank at 938Dispensary Health Services Completed 138,400.00 Chepseon Feedback
Construction of Chebwareng Box Culvert Public Works, Roads and Transport Completed 1,037,760.81 Chepseon Feedback
Construction of Kamuogo-Independent Box Culvert Public Works, Roads and Transport Completed 1,392,307.98 Tendeno/Sorget Feedback
Constaruction of Ainapsosiot-Cheriroet Road Public Works, Roads and Transport Completed 1,781,416.00 Chepseon Feedback
Construction of Binyiny- Sogobet Road Public Works, Roads and Transport Completed 1,803,131.00 Chepseon Feedback
Construction of Kamagaa-Sogobet Road Public Works, Roads and Transport Completed 3,510,347.00 Chepseon Feedback
Construction Maili Nne - Chepnoet Road Public Works, Roads and Transport Completed 1,679,607.60 Chepseon Feedback
Construction of Kamarus - Kamarus Annex - Kamarus school for Disability Ltd Public Works, Roads and Transport Completed 3,999,999.00 Chepseon Feedback
Construction of Chilchila - Lamaiyat Road Public Works, Roads and Transport Completed 3,949,930.00 Chepseon Feedback
Construction of Kichawir - Tata; Kapchomishan -Kaminit; Kapchomishan - Leberer Road Public Works, Roads and Transport Completed 3,649,608.47 Chepseon Feedback
Construction of Chepsir- Arap Kitai - Binyiny road Public Works, Roads and Transport Completed 3,988,767.30 Chepseon Feedback
Construction of Kapseger- sailo Road Public Works, Roads and Transport Completed 5,800,000.00 Chepseon Feedback
Construction of Off B1-Sabunit Road Public Works, Roads and Transport Completed 3,933,500.00 Chepseon Feedback
Kipchawir-Leberer Road Public Works, Roads and Transport Completed 3,400,000.00 Chepseon Feedback
Kolonget-kipchawir Road, Monori-Sailo Road Public Works, Roads and Transport Completed 3,800,000.00 Chepseon Feedback
Tilito-chesumot Road, Chebwagan-kaptenet Road Public Works, Roads and Transport Completed 3,971,577.84 Chepseon Feedback
Construction of Off B1-Chepsir Deliverance church Road Public Works, Roads and Transport Completed 3,722,878.00 Chepseon Feedback
Lambel Road Public Works, Roads and Transport Completed 3,937,040.00 Kedowa/Kimugul Feedback
Construction of Kapchongoti Farm - Tuiyobei Bridge Road Public Works, Roads and Transport Completed 3,648,747.00 Kedowa/Kimugul Feedback
Construction of Delivarance -Ngatumek Road Public Works, Roads and Transport Completed 3,850,742.40 Kedowa/Kimugul Feedback
Culverts Installation to Ewat-Kap Maxwell Road Public Works, Roads and Transport Completed 3,900,080.80 Kedowa/Kimugul Feedback
Ndarugu-Kedowa Centre;Kedowa Centre access roads Public Works, Roads and Transport Completed 3,403,239.72 Kedowa/Kimugul Feedback
Construction of Kapmaxwel-Ewat Road Public Works, Roads and Transport Completed 3,955,739.20 Kedowa/Kimugul Feedback
Tuiyobei-Kedowa river-Kimaut Road Public Works, Roads and Transport Completed 3,345,078.63 Kedowa/Kimugul Feedback
AGC Karanja-Simotwet-Kiptenden Road Public Works, Roads and Transport Completed 3,423,090.00 Kedowa/Kimugul Feedback
Kamwingi two- Shabaa Road,kamwingi center keringet pry, forest Road, Kap pilot -kapkiron Road Public Works, Roads and Transport Completed 1,676,607.60 Londiani Feedback
Kamwingi two- Shabaa Road,kamwingi center keringet pry, forest Road, Kap pilot -kapkiron Road Public Works, Roads and Transport Completed 1,803,131.00 Londiani Feedback
Kaphilemon Road Public Works, Roads and Transport Completed 3,510,347.00 Londiani Feedback
Construction of Kamaina-Sachangwan-Lemotit-Tarmasang Road Public Works, Roads and Transport Completed 1,403,636.40 Londiani Feedback
Construction of Kapfinch-Sotik-Tachasis-Kaplimo-Chumba Road Public Works, Roads and Transport Completed 3,780,440.00 Londiani Feedback
Construction of Nyairobi - Saramek centre- Shabaa Road Public Works, Roads and Transport Completed 1,414,374.00 Londiani Feedback
Construction of Kondamet - Chelalang Road Public Works, Roads and Transport Completed 1,446,341.00 Londiani Feedback
Construction of Hill- tea - Wambare Road Public Works, Roads and Transport Completed 1,403,551.68 Tendeno/Sorget Feedback
Construction of Eastleigh-Independent- Forest Road Public Works, Roads and Transport Completed 3,982,880.00 Tendeno/Sorget Feedback
Construction of Subukia-Mugumoini Road,Mugumoini-Kamuogo Road,Kamwingi-Miti Tatu Road,Subukia-wambare Road Public Works, Roads and Transport Completed 1,395,805.00 Tendeno/Sorget Feedback
Mugumoini-Independent Road Public Works, Roads and Transport Completed 1,496,861.00 Tendeno/Sorget Feedback
Subukia-Kaburi-Mugumoini Road Public Works, Roads and Transport Completed 1,462,262.36 Tendeno/Sorget Feedback