2020/2021 FINANCIAL YEAR PROJECTS

Department: Public Works, Roads and Transport

- All Projects-
Go back

Project Objective Department Status Budget(Kshs) Ward
Cherire - Kisabei Pry- Kiptegan Nursery Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,880,704.00 Kapsoit Feedback
Extension Kenya 1 - Cattle dip - Quarry Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,182,888.00 Soliat Feedback
Kap Eli - Off B1 - Koiyet - Chesanga -Hass Petrol Station- Emanuels Agc Chucrh- Kiboko- Off B1 Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,411,600.00 Kipchebor Feedback
Kapchemirmir TBC - Cherire TBC - Kapsewe Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,696,476.00 Sigowet Feedback
Satelite - Matobo Primary-Nyagacho - Nursery Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 911,900.00 Kipchebor Feedback
Kapchanga - Taiwet - Centre Juu Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,520,910.00 Sigowet Feedback
Baraka Kipsotet-Kimeswon Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 566,575.00 Kipchimchim Feedback
Kapchemirmir TBC - Cherire TBC - Kapsewe Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 822,094.32 Sigowet Feedback
Taiwet - Kipsutet Primary School Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 140,000.00 Kipchimchim Feedback
Kakibei-KMC - Kuche - Kiptenden - Rwandit - Kapchanga Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,616,416.00 Sigowet Feedback
Kap Joseah- Kipsakwa Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,021,000.00 Kipchimchim Feedback
Sigowet - Kaplieli - Sisionik (3Km); Cherote - Kigomba Road (4.1km) To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,080,000.00 Sigowet Feedback
Kapango- Simotwet Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 632,000.00 Kipchimchim Feedback
Sigowet - Kaplieli - Sisionik (3Km); Cherote - Kigomba Road (4.1km) To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,337,300.00 Sigowet Feedback
Routine Maintenance of Kapsegut- Jerusalem Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,645,020.00 Cheboin Feedback
Orgong - Kaplieli - Kalelbusienduk - Kapchanga Road; Tamboiyot - Kitenden - Kebeneti Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,030,540.00 Sigowet Feedback
Routine Maintenance of Ngororga 08 tbc- cheptigit- Sahangwan Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,671,200.00 Cheboin Feedback
Orgong - Kaplieli - Kalelbusienduk - Kapchanga Road; Tamboiyot - Kitenden - Kebeneti Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,918,972.00 Sigowet Feedback
Routine Maintenance of Maburo- Malinja- Bakoiyot Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 560,000.00 Cheboin Feedback
Sinendet Cherire TBC Road; Kapchemirmir Road; Centre juu - Taiywet - Kapchanga Road; Kiptere market Roads. To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,528,300.00 Sigowet Feedback
Routine Maintenance of Off C23- ChemosIt- Chebarema- Kabitungu TBC Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 8,607,424.00 Chemosot Feedback
Sisionik - Chemegong - Kapndege Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,434,200.00 Sigowet Feedback
Routine Maintenance of Off C23- Chemosot Centre- Arap Irongi- Chebulu Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,920,000.00 Chemosot Feedback
Kaplelartet-Tililbei Road;Chepkemel-Sumeek Road; Sumeek-Tililbei Road. To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,958,163.00 Kaplelartet Feedback
Routine Maintenance of Off C23- Kaminjeiwet- Chebulu Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,279,000.00 Chemosot Feedback
Mutwot - Kokwasoi - Emdit Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,645,260.00 Kaplelartet Feedback
Routine Maintenance of Nairobi Ndogo- Kimauto Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 910,000.00 Cheplanget Feedback
Chepkemel Centre - Arap Cheruiyot - Sumeek Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,633,960.00 Kaplelartet Feedback
Routine Maintenance of Tabaita- Kap Johna Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,598,400.00 Cheplanget Feedback
Kaplelartet - Arap Cheruiyot - Sumeek Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,553,340.00 Kaplelartet Feedback
Routine Maintenance of Twoliot- Church Of Christ- Tangit- Sebetet- Ainapkarik Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,800,000.00 Cheplanget Feedback
Mutwot - Kokwasoi - Emdit Road; Chepkemel Center - Karap Cheruiyot Road; Kapmorok - Chepkemel TBC - Centre Road; Chepchelalemit - Sime Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,014,000.00 Kaplelartet Feedback
Routine Maintenance of Nuru- Meturi Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 865,000.00 Kapkatet Feedback
Mutwot - Kapkawa- Kiplekwa pry School Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,498,000.00 Kaplelartet Feedback
Routine Maintenance of Chebitet- Kap Tebengwet Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,183,180.00 Kapkatet Feedback
Kaplelartet - Kapsomboch Primary School Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,753,400.00 Kaplelartet Feedback
Routine Maintenance of Chebitet Sign Post- Sachangwan Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,650,000.00 Kapkatet Feedback
Kona Sita - Sumeek Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,975,000.00 Kaplelartet Feedback
Routine Maintenance of Sachangwan- Mabasi TBC- Ketingoi Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,987,000.00 Kisiara Feedback
Rehabilitation and Construction of Lelagoi- Yanja- Karap Maina Road 4.5Km To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 8,578,680.00 Sigowet Feedback
Routine Maintenance of Keregut- Sikongo Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,964,800.00 Kisiara Feedback
Rehabilitation of Drainage Structures and access roads in Kapkatet Market To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,614,856.00 Kapkatet Feedback
Routine Maintenance of Machorwa- Chomisian- Charera To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,730,000.00 Kisiara Feedback
Rehabilitation and Construction of Kapias- Timbilil-Kamotos Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 7,457,528.00 Kunyak Feedback
Routine Maintenance of Kelelwa- Kimugul Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,672,480.00 Kisiara Feedback
Routine Maintenance of Kap Ezekiel Centre- Kipkwes Pry School-Kipchorian River- Kipchorian Bridge Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,113,000.00 Ainamoi Feedback
Routine Maintenance of Reresik Pry- Kiprichait- Roret Boys- Chebululu- Tulwet- Ngainet Bridge Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,608,880.00 Kisiara Feedback
Routine Maintenance of Yasomok-Kamelilo Coffee Factory-Kiburet Pry School Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,324,708.00 Ainamoi Feedback
Routine Maintenance of America- Sinendet Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,151,160.00 Litein Feedback
Ainamoi centre-berea AIC Church-Pakao-Delivarance-Kap Jona To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,281,920.00 Ainamoi Feedback
Routine Maintenance of Bushmouth- Samuget- Kap Brown - TTC Valley Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,646,520.00 Litein Feedback
Grading Of Kipchimchim Sec-Kabotris Road, Kabotris-Kondamet Road,Kapcheptoror-Sirimdo Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,455,700.00 Kipchimchim Feedback
Routine Maintenance of Kapkarin- Chesoen TBC Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,503,600.00 Litein Feedback
Construction of Kiptabo TBC-Chepkosilen sec-Ainap Isirek-Bondeni road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,329,016.00 Cheptororiet/Seretut Feedback
Routine Maintenance of Ainapset AIC- Kapbomwo- Rungut Pry- Chepsembe- Tendwet TBC Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,704,050.00 Litein Feedback
Construction of Chomisian- Ngariet Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,629,200.00 Kisiara Feedback
Routine Maintenance of Chepkitach- Kipsagetet Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,279,860.00 Tebesonik Feedback
Construction Of Chepkitar Centre- Toroton Boundary- Yalla Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,516,740.00 Chilchila Feedback
Routine Maintenance of Kibaranji- Karapngerer Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,434,628.00 Tebesonik Feedback
Grading of Chilchila- Murgut Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,484,640.00 Chilchila Feedback
Routine Maintenance of Kibolgong-Tiritab Eito Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,326,050.00 Tebesonik Feedback
Kisumu Ndogo-TBC-Melit r, Kapsamba-Kamasian Road, Kimungen Road,Dispensary-KamasianRoad, maso Market-Maso sch Road; Maso Shopping -Maso Church Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,656,736.00 Kamasian Feedback
Routine Maintenance of Silva Junction- Siongi- Kampala Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,697,305.00 Tebesonik Feedback
Kiprengwe Pry School- Miti Moja Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,189,694.00 Kedowa/Kimugul Feedback
Routine Maintenance of Chebirirbei Centre- Chepnagai Pry School Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,603,520.00 Kabianga Feedback
Masaita - Itoik - 936 farmers Road 5.4km To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,078,550.00 Londiani Feedback
Routine Maintenance of Kapsisiywa Pry- Kipseger TBC- Sinonin Pry Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,359,540.00 Kabianga Feedback
Routine Maintenance of Mobego B TBC- Nyabangi Sec. School- Kolonget Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,951,040.00 Kabianga Feedback
Routine Maintenance of Kaplutiet- Kiptuigo- Ainabisarak Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,503,600.00 Kabianga Feedback
Routine Maintenance of Bot Musa- Cheboin- Kimolwet- SBI- Kugerwet Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 7,882,712.00 Kapsuser Feedback
Routine Maintenance of Cheptororiet- Arap Tanui Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,167,040.00 Kapsuser Feedback
Routine Maintenance of Kamungwana- Bae-kaplemeywet- Kapnandet Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,037,140.00 Kapsuser Feedback
Routine Maintenance of Changoi Road- Boito- Kapburkei- Mlimani Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,251,970.00 Cheptororiet/Seretut Feedback
Routine Maintenance of Cheswerta AGC- Chepkutbei Bridge Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,149,890.00 Cheptororiet/Seretut Feedback
Construction of Kaprongori- -Kaproret Road; Tulwet-Ngianet Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,925,328.00 Kisiara Feedback
Routine Maintenance of Kipsolu pry- Soweto TBC- Michingilwet- Cherigat Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,551,740.00 Cheptororiet/Seretut Feedback
Routine Maintenance of Darajet-Barekeiwet dinspensary-Arap Maina-Mungenik road Potholes patched, ,surface grading completed. Public Works, Roads and Transport Completed 6,423,960.00 Soliat Feedback
Routine Maintenance of Kosachmwai- Chemoset Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,098,550.00 Cheptororiet/Seretut Feedback
Routine Maintenance of Off D312-938 Girls Road Potholes patched, ,surface grading completed. Public Works, Roads and Transport Completed 1,288,392.00 Chepseon Feedback
Routine Maintenance of Cheptenye Sign post- Off Sosiot- Keben Pry Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 7,801,748.00 Waldai Feedback
Routine Maintenance of Mark Peter- Off Kabianga- Chemumbe- Kaborok Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 11,192,013.00 Waldai Feedback
Routine Maintenance of Off Cheribo- Ngariet Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 350,000.00 Waldai Feedback
Routine Maintenance of Off D314- Mutanya Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,794,100.00 Chepseon Feedback
Routine Maintenance of 938 - Central Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,420,780.00 Chepseon Feedback
Routine Maintenance of Kipyobob Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,214,000.00 Chepseon Feedback
Routine Maintenance of Chesinende Catholic- Koibarak Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,596,712.00 Chepseon Feedback
Routine Maintenance of D314- 938 Girls Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed N/A Chepseon Feedback
Routine Maintenance of Off B1- Ewat Kap Maxwel - Catholic- Kiplekwa Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,438,000.00 Kedowa/Kimugul Feedback
Routine Maintenance of Off C35- Ndiwa Cattle Dip Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,194,000.00 Kedowa/Kimugul Feedback
Routine Maintenance of Slaughter House- Towet Bridge- Maridany Forest Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,422,100.00 Tendeno/Sorget Feedback
Routine Maintenance of Kapkondoo Centre- Silibwet Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 717,950.00 Londiani Feedback
Routine Maintenance of Kapcheplanga Centre- Martina Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,114,000.00 Londiani Feedback
Routine Maintenance of Elite Primary School- Chebangang Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,288,730.00 Londiani Feedback
Routine Maintenance of Sachangwan- Kap Tilia Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 7,883,590.00 Londiani Feedback
Routine Maintenance of Barotion- Sawmill- Lelsotet Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,724,750.00 Londiani Feedback
Routine Maintenance of Burutu- Kamiwa- Kapkese Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,210,500.00 Chilchila Feedback
Routine Maintenance of Factory Junction- Kamiwa- Kapkese Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,642,380.00 Chilchila Feedback
Routine Maintenance of Tunnel- Chumbeek Dispensary Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,783,630.00 Chilchila Feedback
Routine Maintenance of Mutai- Lelei Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,314,020.00 Kamasian Feedback
Routine Maintenance of Nyairobi- Songonyet Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,627,540.00 Kamasian Feedback
Routine Maintenance of Murau Centre- Bakery Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,101,700.00 Kamasian Feedback
Routine Maintenance of Off C35- Segetet- Murau Brige Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,180,000.00 Kipkelion Feedback
Routine Maintenance of Kamore- Kap Sephania Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,268,400.00 Kipkelion Feedback
Routine Maintenance of Kap Onyango-Kapkwen Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,423,800.00 Kunyak Feedback
Routine Maintenance of Sachangwan- Mariwa Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,211,800.00 Kunyak Feedback
Routine Maintenance of Chesino- Kapkormom- Koiyabei Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,420,720.00 Soin Feedback
Routine Maintenance of Kipsitet Cattle Dip- Asenwet-Kap Musar Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,749,000.00 Soin Feedback
Routine Maintenance of Chemaluk- Gladys Canteen- Bokwo Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,352,400.00 Soin Feedback
Routine Maintenance of Soliat Corner – Kaplengeny – Kiptugumo Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,363,060.00 Soliat Feedback
Routine Maintenance of R47- Chebaran Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,949,360.00 Soliat Feedback
Routine Maintenance of Cheramor Centre- Kipkerer Bridge- Arap Bore Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 735,000.00 Soliat Feedback
Routine Maintenance of Tarajet- Baregeiwet Dispeensary- Karap Maina- Mungenik Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 667,800.00 Soliat Feedback
Routine Maintenance of Salgaa- Kongeren River- Kap Laiba Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,360,800.00 Soliat Feedback
Routine Maintenance of Kakibei- Kapchemirmir- Mutata- Chepkochun Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,216,900.00 Sigowet Feedback
Routine Maintenance of Sisionik- Tumoyot Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,600,412.00 Sigowet Feedback
Routine Maintenance of ML 10- Chebetet- Kalyongwet TBC Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,503,850.00 Kaplelartet Feedback
Routine Maintenance of Mutwot - Emdit Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,190,012.00 Kaplelartet Feedback
Routine Maintenance of Kaplelartet Chief’s Office- Tabaita Centre Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,166,000.00 Kaplelartet Feedback
Construction of Kerego Box Culvert at Kwa Silvan- Kids home - Kerego To improve road safety and accessibility Public Works, Roads and Transport Completed 2,082,900.00 Kapkugerwet Feedback
Construction of Ainapkosobin 3X900mm cross culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 1,441,600.00 Kapkugerwet Feedback
Construction of Twin 900mm cross culvert at Wema - Chemugusu Road To improve road safety and accessibility Public Works, Roads and Transport Completed 2,179,800.00 Kapkugerwet Feedback
Construction of Torsogek Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 3,794,800.00 Kapsoit Feedback
Construction of Jordan Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 1,816,604.00 Kapsoit Feedback
Construction of Mjini Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 2,609,944.00 Kipchebor Feedback
Construction of Gokul- Kamelilo Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 4,264,692.00 Ainamoi Feedback
Installation of 10 lines of 600mm along Arap Cheruiyot- Maberiat AGC Church Road, Budalangi-Totlilet- Mureret Road To improve road safety and accessibility Public Works, Roads and Transport Completed 1,015,000.00 Ainamoi Feedback
Construction of Koigaron Twin 900mm cross culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 1,251,860.00 Kapsaos Feedback
Construction of Buchenge Deck for Bridge To improve road safety and accessibility Public Works, Roads and Transport Completed 4,696,800.00 Kapsaos Feedback
Construction of Kisabei Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 1,124,500.00 Kapsoit Feedback
Construction of Sugutek Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 391,680.00 Kapsoit Feedback
Construction of Kapsinei Mini Bridge To improve road safety and accessibility Public Works, Roads and Transport Completed 2,120,000.00 Kapsoit Feedback
Construction of Kapsakwa Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 4,028,000.00 Kipchimchim Feedback
Construction of Kimugen Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 6,360,000.00 Kipchebor Feedback
Construction of 600mm cross culvert to Kaborus - Chabasta road 2km To improve road safety and accessibility Public Works, Roads and Transport Completed 4,006,800.00 Cheboin Feedback
Construction of 600mm cross culvert to Koitamat - Cheptenteniet road 3km To improve road safety and accessibility Public Works, Roads and Transport Completed 4,900,000.00 Cheboin Feedback
Construction of Machorwa- Kapcheluch Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 4,256,960.00 Kisiara Feedback
Construction of Senetwet Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 8,492,300.00 Cheplanget Feedback
Construction of Kisiara -Kap nyongo Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 2,300,900.00 Chemosot Feedback
Construction of Kaptebengwet - Cheptangulgei Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 4,347,060.00 Kapkatet Feedback
Construction of Chematich-Kaptirbet Twin 900mm Cross Culverts To improve road safety and accessibility Public Works, Roads and Transport Completed 560,000.00 Kapkatet Feedback
Construction of Kabusienduk Twin 900mm Cross Culverts To improve road safety and accessibility Public Works, Roads and Transport Completed 4,197,600.00 Tebesonik Feedback
Construction of Chesebet Pipe Culverts To improve road safety and accessibility Public Works, Roads and Transport Completed 3,308,360.00 Kabianga Feedback
Construction of Nyabangi Road Culverts To improve road safety and accessibility Public Works, Roads and Transport Completed 3,216,040.00 Kabianga Feedback
Construction of twin 900mm cross Culvert at Arap Kitur - Arap Serem Road To improve road safety and accessibility Public Works, Roads and Transport Completed 6,701,830.00 Kapsuser Feedback
Construction of Twin 900mm cross Culvert at Cheboin river To improve road safety and accessibility Public Works, Roads and Transport Completed 3,503,150.00 Kapsuser Feedback
Construction of Twin 900mm cross Culvert at Arap Samityuk - Kap Christopher Road To improve road safety and accessibility Public Works, Roads and Transport Completed 2,226,000.00 Kapsuser Feedback
Construction of Chepkutbei Pipe Culverts To improve road safety and accessibility Public Works, Roads and Transport Completed 2,249,000.00 Cheptororiet/Seretut Feedback
Construction of Kipkeremwo twin 900mm Cross Culverts To improve road safety and accessibility Public Works, Roads and Transport Completed 5,992,400.00 Chepseon Feedback
Construction of twin 900mm cross culvert at 938 dip Road To improve road safety and accessibility Public Works, Roads and Transport Completed 3,428,720.00 Chepseon Feedback
Construction of Silibonik-Kiplekwa Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 10,526,200.00 Kedowa/Kimugul Feedback
Construction of Off B1 - Lembel Culverts To improve road safety and accessibility Public Works, Roads and Transport Completed 7,120,904.00 Kedowa/Kimugul Feedback
Construction of Cross Culverts to Chebitet- Kipyemit Road To improve road safety and accessibility Public Works, Roads and Transport Completed 1,590,000.00 Kedowa/Kimugul Feedback
Construction of precast culvertsat Nairobi - Saramek Road To improve road safety and accessibility Public Works, Roads and Transport Completed 3,969,330.00 Londiani Feedback
Construction of precast culvert to Chelalang - Kondamet Road To improve road safety and accessibility Public Works, Roads and Transport Completed 3,731,680.00 Londiani Feedback
Construction of precast culverts to Kafinch - Sotik Road To improve road safety and accessibility Public Works, Roads and Transport Completed 2,204,800.00 Londiani Feedback
Construction of Lelsotet Bridge To improve road safety and accessibility Public Works, Roads and Transport Completed 1,632,400.00 Londiani Feedback
Construction of Koisagat - Chilchila Boundary Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 3,460,060.00 Chilchila Feedback
Construction of Segetet - Kitobe Twin twin 900mm cross Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 3,325,250.00 Kipkelion Feedback
Construction of Mogire Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 7,624,000.00 Chilchila Feedback
Construction of Soi Mingin - Blue Hills Cattle Dip Twin 900mm Cross Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 4,791,300.00 Kipkelion Feedback
Construction of Minihaha Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 743,900.00 Kunyak Feedback
Construction of Nunda Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 2,158,400.00 Soin Feedback
Construction of Kapaiwo twin 900mm Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 2,595,000.00 Soliat Feedback
Construction of Kongeren twin 900mm Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 6,164,640.00 Soliat Feedback
Construction of Sombicho Twin 900mm Culverts Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 5,117,200.00 Soliat Feedback
Construction of Orgony Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 8,391,800.00 Sigowet Feedback
Construction of Sime Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 1,608,900.00 Kaplelartet Feedback
Construction of School of Excellence Box Culvert To improve road safety and accessibility Public Works, Roads and Transport Completed 2,650,000.00 Kaplelartet Feedback
Budalangi-Bechulelach-Kipchorian rd; Kaptongilo-Cheplit rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,158,400.00 Ainamoi Feedback
Kiburet-Factory- Yasomok Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,988,720.00 Ainamoi Feedback
Ketpyse rd;Kamelilo rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 224,774,768.60 Ainamoi Feedback
Ainamoi Polytechnic - Kapsengerini rd (2Km); Ainamoi Sub County Hospital (0.5Km); Kapjonah - Bagao rd (5Km); Ainamoi bridge – Maseriat AGC Rd (2km) To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 15,363,827.10 Ainamoi Feedback
Ainamoi Shopping centre- Ainamoi pry- Itibet road; Senetwet - Arap Cheruiyot - Maberiat FGC rd; Kamelilo coffee factory - Kamelilo pry - Arap Ngeny rd; Kamelilo pry - Koisirat rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 46,884,040.00 Ainamoi Feedback
Lelechwet - Mureret rd; Ainamoi town To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 8,941,017.66 Ainamoi Feedback
Ainamoi Market - Ainamoi pry - Itibet rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 25,984,788.64 Ainamoi Feedback
Senetwet - Arap Cheruiyot - Maberiat FGK rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 242,660.00 Ainamoi Feedback
Kakobirit - Karapbii rd; Kapkeregu - Budalangi - Kapcosmas - Sitini rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,153,168.00 Ainamoi Feedback
Lelechwet - Arap cheboiyon rd; Kaptongilo - Kapchepngok rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,058,746.00 Ainamoi Feedback
Kamelilo factory - Karapngeny rd; Kamelilo pry sch - Kapseremiot river rd; Kapkenat - Kapboniface Kilii rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,914,380.00 Ainamoi Feedback
Ainamoi Centre rd/Bagao To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,444,376.00 Ainamoi Feedback
Keongo Pry School ground leveling To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,402,200.00 Kapkugerwet Feedback
Keongo-Kapsigong Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,950,340.00 Kapkugerwet Feedback
Chemugusu rd; Laibon Town rds; Keongo - Sumeiyon Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 7,309,772.00 Kapkugerwet Feedback
Roads at Kapkurgwet ward To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,019,544.00 Kapkugerwet Feedback
Arap Bii - Chemugusu Rd (2km); TG 12TBC - Kapgregory (2km) To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,231,788.00 Kapkugerwet Feedback
Arap Bii - Chemugusu Rd (2km); TG 12TBC - Kapgregory (2km); Keongo FGCK - Kapturungi rd (2km; Masengo - Laibon rd (2km); Kondamet - Agc - Ngororoga rd (2km); Nukiat - Catholic - Keongo rd (2km) To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,272,892.00 Kapkugerwet Feedback
Keongo - Quentete - Sumeiyon Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 712,320.00 Kapkugerwet Feedback
Chemugusu - Satelite rd; Tea point - Paksonrd; Eland Academy - Majengo - St. Patrick rd; Site and Service- Kericho Academy - Talai rd; Tea Hotel - Kimugu Treatment works rd; Quintete - Talai rd; Off B1 - Duka Moja Junction rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,664,200.00 Kapkugerwet Feedback
Kapsilangwa-Ainapsosiot rd;Kapoldoit-Kaprewet rd;Chesumot rd;Binyiny rd ;Mureret rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 600,600.00 Kapsaos Feedback
Kipsigori - Kapsaos Centte rd; Off C35 - Lamaiyat pry - Torochgaa brdige rd; Kapngetuny rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,017,604.00 Kapsaos Feedback
Tabet-Koigaron-Mureret-Kipsigori-Kamuungei road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,293,900.00 Kapsaos Feedback
Kapsoit-Kaboswa- Kimasian-Kiboibei-Slaughter hse road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,135,256.00 Kapsoit Feedback
mongo- Chepkut rd; Kenegut-Chepkel TBC-Chesire rd; Kenegut MKT-Kisabei Pry-Kiptegan Nursery rd; Kapsoit- Kaboswa-Kimasian-Kiboibei-Slaughter rd; Off b1-Ngecherok AGC-Chepkurbet Pry road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,483,160.00 Kapsoit Feedback
Off B1-Chemobei rd;Off B1-Chepkurbet AGC;Off B1-Ngecherok AGC rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,201,828.00 Kapsoit Feedback
off E222-Kaptoroi-Kiptenden rd;Muiwek-Tuiyobei rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,034,020.00 Kapsoit Feedback
Kara Tegerei - Gabel rd; Tilrap Malit - Kirongisyet rd; John Bett - Kirongisyet rd; Kaptimothy - Chelule rd; Chemoibei pry - Koitabai rd; Arap Kenei - Kiptendon Rd; Kiptendon - Lemeiywet rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,742,792.00 Kapsoit Feedback
Water tank - Sachangwan - Ngecherok AGC - Off B1 - Sachangwan - Chepkubet pry sch; Off B1 - Full Gospel Church - Samutet central; Off B1 - Kongosiet - Siitotwet; Sitotwet - Jordan rd; Off B1 - Chepsoo rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 207,600.00 Kapsoit Feedback
Water tank - Sachangwan - Ngecherok AGC - Off B1 - Sachangwan - Chepkubet pry sch; Off B1 - Full Gospel Church - Samutet central; Off B1 - Kongosiet - Siitotwet; Sitotwet - Jordan rd; Off B1 - Chepsoo rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,890,916.00 Kapsoit Feedback
Kichinjet - Kaboswa rd; Karap Tergei - Chepsoo rd; Kamundu rd; Samutet pry - Chemobei rd; Samutet - Kappeter rd; Karap Teregei rd; Tiles - Karap Barjwot rd; Toro - Kameshak rd; Sitotwet - Kirongishet rd; Koitabai rd; Karap Tererei - Gable rd To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,320,760.00 Kapsoit Feedback
Sailo-Chepcholiet Road; Chesumei-Tugunon Road; Sebere-Chesumei Road; Kapsegut- Nyambuko Road; Cherendet-Kiptenden Road. To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,048,400.00 Chepseon Feedback
Mandera-Kipketes Road; Chepcholiet-Tugunon Road; Leberer-Mile Tano; Kamachungwa-Factory Road; Momoniat-Chepchabai Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,236,820.00 Chepseon Feedback
Kiptenden - Kamarus Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,320,760.00 Chepseon Feedback
Kaptenet - Chebwareng - Kipchorian Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,433,480.00 Chepseon Feedback
Kaptenet - Fredrick Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,761,840.00 Chepseon Feedback
Kapsokwe - De;iverance - Kipyoptop Road; Kaptenet - Fredrick - Scheme Road; Kapeli - Tilito - Kaisugu Road; Kapfredrick - Ketienya - Chebochok Road; Kapketungor - Maseti Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,758,660.00 Chepseon Feedback
Off B1 Wima Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,924,540.00 Chepseon Feedback
Tenbwet - Complex Road; Kiprengwe - Miti mbali Road; Kipsigori - Kiprengwe corner Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 742,000.00 Chepseon Feedback
Siwot - Motanya; Cheboror;Kondamet/ Mutanya - Kapkawa Road ; C woRoad - Ka[somting - Kiptenden Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,520,940.00 Chepseon Feedback
Siwot Motanya To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,434,480.00 Chepseon Feedback
B1-Kedowa-Ewat road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,371,330.00 Kedowa/Kimugul Feedback
Kedowa River farm-Kimaut-Barngoror Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,313,920.00 Kedowa/Kimugul Feedback
Ewat - Forest Road; Ndarugu - Kapchebotibiot - Timbilet Road; Kiprengwe - Miti moja - Kapmabwai Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,313,920.00 Kedowa/Kimugul Feedback
Kipyemit Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,524,060.00 Kedowa/Kimugul Feedback
Off B1 - Tulwap Road; Road Unit - Kolonget Road; Nyakinywa Roads To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,702,561.00 Kedowa/Kimugul Feedback
Kaap Nashon - Kipkoiyo pry (3km); Off C35 - Wispers - Kiptenden Road (2.5km) To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,099,500.00 Kedowa/Kimugul Feedback
Rehabilitation and Construction Drainage Strutures and Tarmacking of 936 Town To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,700,240.00 Kedowa/Kimugul Feedback
Lembel Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 830,400.00 Londiani Feedback
Jagoror center- Kerembe road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,162,200.00 Londiani Feedback
Jagoror center-Cypress Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,727,576.00 Londiani Feedback
Off C35 - AIC 936 Academy-Lolongbei Pry Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,272,000.00 Londiani Feedback
off C35 -Engineer Rotich-Nukiat-Link 35 Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,639,820.00 Londiani Feedback
Construction of 28m of 600mm and twin 900mm Cross Culvert at Chepkemel Cetre- Arap Cheruiyot- Sumeek Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 7,602,908.00 Kaplelartet Feedback
Kabarak ECDE - Sachangwan Road 2.8km; Off D 254 -Gishorio Road 1.5km; Kapsenda - Lolonbbei Road 1.3km; Kapchepkorio - Quarry Road0.4km; Kapsenda Dispensary - Chebaraa Road 1.7km; Satek - Langat Road 1.4km To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,541,324.00 Londiani Feedback
Barotion pry - Lelsotet Road; Barotion pry - Arap Chief Road; Kaptien - Sorget Road; Miti mingi - Kwa DC - Kaptich Road; To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,913,048.00 Londiani Feedback
Sirako - Jerusalem Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,163,400.00 Londiani Feedback
Chinese - Kapsegut Road; Lalanggbei Road; Kapjunior - Kiplangat Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,814,156.00 Londiani Feedback
Chinese - Kapsegut Road; Lalanggbei Road; Kapjunior - Kiplangat Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,589,548.00 Londiani Feedback
Tegat - Lelsotet Road; Dr Ngeno-Roadunit To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,520,400.00 Londiani Feedback
Turienga - Barotion boRoader Road; Off Lemotit Road - Njia Mpya - Link C35 Road; Kapcheplanga sec sch - Kapcheplanga pry - Kap Musa - Good luck Academy Road; Kap matthew - Kamaritim Road; Kapkondoo Junction - Kapcentre quarry Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,252,418.00 Tendeno/Sorget Feedback
Turienga - Barotion boRoader Road; Off Lemotit Road - Njia Mpya - Link C35 Road; Kapcheplanga sec sch - Kapcheplanga pry - Kap Musa - Good luck Academy Road; Kap matthew - Kamaritim Road; Kapkondoo Junction - Kapcentre quarry Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,815,400.00 Tendeno/Sorget Feedback
Tendeno dip-Kariuki Road;Tumaini sec-Kericho boRoader-Nominated MCA Road;Kienyere Road-Ndoiro Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,601,180.00 Tendeno/Sorget Feedback
Centre one-Cheborge Road;CheborgeMarsin Road;Miti tatu-Lovito-Kolonget Road;Kongoni dispensary-Chepkok Road;Singoi-Gwitu pry Road;Ayondi-Atiokigit river Road;Chabaya-Kichagi Road;Chabaya-KiMuremi Munga Road;Leltae-Kosigu-Captain Road;Towet-Kimager Road;Cheriro-wokter-mokiolok Road; E254-kk-Mwano-Muoroto-Siangatia Road;Chege-Wamutu-Wamagi Road;Zakao-kag church Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,578,400.00 Tendeno/Sorget Feedback
Kapsabet-Bagdad Road;Muikamba-David Mtaro Road;Emmanuel-PCA Road-Kaburi Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,602,720.00 Tendeno/Sorget Feedback
Tendeno-SubukiaRoad;Subukia-Wambare Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,807,140.00 Tendeno/Sorget Feedback
Miti - tatu - Benditai Road; Chebusit main road - JXN road; Chemororen - Kamau Nubery Road; Rajab - CHEMWOKTER ROAD; Chebaibai - Kapkimoi nRoad; Kimoi - Kamaua; Rajab - Busara Road; Chebaibai - Ximboiyo Road; Cheborgei - Seronei Road; Seronei - Benditai BoaRoader Road; Mikingo - Bridge Road; Maritim - Kimoi Road; Sach 4 - Barno Road; Bitok - Yegen Selim -KAcheyat Road; KAptembwo - Forest Road; Maranget - Chemwokter Road; Chebubto - Cheriro Road ; Chebaibai - Louito Road and Simboiyon Sach 4 Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 7,999,960.00 Tendeno/Sorget Feedback
Kahuho Road; Tumaini Road; Kaigemi Ak foRoad Road; Wangare- MCA Road; Mukamba - mulkaroubo Road; Mahinga - Borchek Road; Subukia - Independent Road; Mburu - Dave Road; Independent - Isili - Tendeno pry Road; Nginga - Kamwingi Road; Independent church - Nginga Jxn Road; Micheal JXN- Mwangi Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,175,040.00 Tendeno/Sorget Feedback
Construction of Kamwingi II - Kiangundo Road;Kamwingi pry - KIMARI - Singati Road; Centre 1 - Majani Road; Taarifa corner Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,575,028.00 Chilchila Feedback
Kaigai Road; UPC raod; Majani sawmil Awii; Amos Saiz Road; Independent church - Dam Road; Catholic main -Cherer diversion Road; Macam Milka - Koigo Road; Cheres Road; Chebangang Road; Josh dam Road; Chane rs; Upendo Road; Akimani Road; Zakayo Road; Mama Mike Road; Mrs Langat - Forest Road; Botpla Road; Mama wangari cam Daniel Road; Speaker Kipronon Road; Kwa Daniel Road; Daniel Forest Road; Centaa Roads; Kipkelion works; Barsiele Road; Mau Road; Power Road; owet Guito Road; Ngingo - highway Road; Peters - gwitu Road; Bungowma - Roisili Road; Assembly Church Bridge - Bridge cheres Road; Bridge Road; Assembly Church - bridge Road; Cheres - Bridge Road; Mama chelimo Al shabaab Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,473,400.00 Chilchila Feedback
Kwa Chief-Jagoror Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,363,196.00 Chilchila Feedback
Kokwet-Toroton-Kipsasur Road;Bomore-Kap Chapati Road;Kokwet Centre Road;Momugut-Kapinguron;Chemunyala-Store Road;Sachangwan-Kapchorua Road;Burutu-Kapkesee Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,847,512.00 Chilchila Feedback
Off Chilchila Sch.-Kapedo Road-Chepkendi Dispensary-Railway Chemunyala Factory-Nyanza Road;Chepkendi-Kapkures Road;Cherara-Kamaget-Murgut Road;Kaplelit-Kishara-Kamatos Road;Kaplelit-Tegat-Timbil Road;Yala-Teldet Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,942,132.00 Chilchila Feedback
Ndubusat-Kaburenik Forest Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,102,860.00 Chilchila Feedback
Murgut Pry Sch.- Nyanza Boundary Road (1.3km); Off E 250 - Karap Murel Road (0.6km); Koisagat - Kapchebere - Morombit Road (0.8km) To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,670,580.00 Chilchila Feedback
Morombit - Morombinyik To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,082,780.00 Chilchila Feedback
Tendwet - Yalla - Kipteres Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,147,363.00 Chilchila Feedback
Teldet Centre - Kortende - Forest Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,426,690.00 Chilchila Feedback
Chepkechei - Kaplekwa - Kipteris FGIK Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,872,280.00 Chilchila Feedback
Chepkitar Centre - Toroton Boundary - Yalla Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,251,040.00 Chilchila Feedback
Toroton - Tulwapmoi Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,282,200.00 Chilchila Feedback
Chilchila Quarry(Tinderet Forest Road) To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,007,926.00 Kamasian Feedback
Tendwet - Malinja - Magire Dispensary Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,942,712.00 Kamasian Feedback
Misoi-Chumba Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,191,360.00 Kamasian Feedback
Kipsongol-Kap Luso-Chemongen Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,952,704.00 Kamasian Feedback
Kasheen-Morao Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,459,964.00 Kamasian Feedback
Kimeto-Kaplaba Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,704,032.00 Kamasian Feedback
Kasheen-Borowet-Murau Pry Sch. Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,553,241.00 Kamasian Feedback
Muharate-Nyairobi-Jagoror Road;Jagoror-Some Road;Jagoror-Kap Sharack Road;Makutano-Nyairobi Sec Road-Kiplaba-Kimologitbridge Road-Kap Sugurup-Greenland Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,134,000.00 Kamasian Feedback
Lelu Centre-Corner Junction Road 3.7KM;Kamtego-Monastry Road 1.2km;Of D312 -Lelu Dispensary Road 15km To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,116,050.00 Kipkelion Feedback
Kapsugurup - Greenland - Kichagi Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,450,064.00 Kipkelion Feedback
Siret Centre-Siret Quarry; Chemager Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,553,241.00 Kipkelion Feedback
AGC-Machilil Road; Tuiyobei- Arap Ngeno-Tilolwet Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,134,000.00 Kipkelion Feedback
Faith Church-Arap Moi Road;Chepkei-Chepkolon Road;Chepkiber-Kaplekwa-Kapkiyao Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,069,688.00 Kipkelion Feedback
Quarry -Fuko Coffee Society Road; Quarry - KitobenRoad To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,242,810.00 Kipkelion Feedback
AGC - Kipchorian - Machilil Road; Tuiyobei - Arap Ngeno - Tilolwet Road; Barsiele Centre - Chorwet Pry - Sugutek Road; Trailor - Kapsoheria Road; Cereal - Magunia Road; Sachwangan - Belsoi Road; Katepia - Mama Major Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,618,532.00 Kipkelion Feedback
Kobiro-Macheisok Road 5km;Miti Moja-Blue Hills Dip Road 3km; Kimologit-Blus Hilss Road 5km To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,217,234.00 Kipkelion Feedback
Agc - Kipchorian - Machilil To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,614,693.00 Kipkelion Feedback
Tuiyobei - Arap Ngeno - Tilolwet Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,134,000.00 Kipkelion Feedback
Barsiele Centre – Kipchorian – Machilil Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,493,844.00 Kunyak Feedback
Off Main Road - Chemagel Road; Siret Centre Coffee Factory Road; Kimologit Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,763,520.00 Kunyak Feedback
Kiptenden Kapkurin Road; Kapkurin-Kamiron Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,561,740.00 Kunyak Feedback
Nyanza- Girimori - Kapkwen Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,071,160.00 Kunyak Feedback
Kapkwen - Chesonoi - Kabirong - Kapkurin - Kiptenden Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,086,463.00 Kunyak Feedback
Minihaha - Sirgoi Pry Sch Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,438,585.00 Kunyak Feedback
Dip - Kolonget - Ngebebo Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,210,708.00 Kunyak Feedback
Kotetni - Chemunyala - Cherara Road 4.5km; Chepsii - Kapsale Pry - Chemunyala Road 3.2km; Chelalo - Kilengel Road 3.1km; Timbilil - Ngola Road 2km; Kabirong - Kapkwen Road 3.5km To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,630,143.00 Kunyak Feedback
Kipsitet-Mbasa Road; Kipsitet bridge-Kaplabotwo Road; Ngeremwo-Kipsitet dip Road; Nunda-Kipteran Road; Kipteran-Nyaberi Road-Laitigo pry-Maemba Road; Laitigo pry- kapsermi Road; Kapsimingoi-Ndanyomare Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,467,128.00 Soin Feedback
Kabore-Cheptililik Road; Cheptililik-Kapkatit Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,882,330.00 Soin Feedback
Ngeremwo-Chebotot Road; Maemba Road; Mbasa Road; Asenwet Road; Cheptagum Road; Laitigo primary Road; Koitaburot Road; Kapkatit Road; Cheptililik Road; Cheptororwo Road; - kipteran-Chepsengeny Sch; ndonyomare Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,145,134.00 Soin Feedback
Tobentai-Kipyoren-Kapkormom Road;Moetik-Tobentai;Kap Macharia-Kipyoren Road,Kap Gravel-Chemaluk Road;Kaplelach-Kwondop Morsong-kaplelach Bridge -Chepsengeny Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed N/A Soin Feedback
Ngeremwo-Chebotot Road (6km) and Kwa Michael -Laitigo (4km) To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,989,046.20 Soin Feedback
Kapkormom Pry - Kapkormom Dispensary Road - Kejiryet - Kaplaboitwa- Sideways - Kapchoge - Laitigo-Ngeremwo Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,588,980.00 Soin Feedback
Kongeren river- Birirbei-Kapchelemei Road; Arap Chebochok-Arap Chepkoit; Kongeren pry Road; Kap Ingok-Birirbei Road; Chepkoson Road; Chepkoson-Kapsigilai Road; Kapchesilim-Kabokyek cattle dip road; Arap Seronik-sesgaa Road-Sesgaa-Kapsegut Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,043,160.00 Soliat Feedback
Itibet - Bagao- Deliverance Church Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 10,338,300.00 Ainamoi Feedback
Soliat corner-Kiptugumo pry Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed N/A Soliat Feedback
Kiburet- Factory- Yasomok Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,205,220.00 Ainamoi Feedback
Kaplaba-kiptare-Kapcheptoo Road-kapkenyele Road;Kurabei-koyabeyon Road;Kurabei-Chesunut-Kapsigowo Road;Kapsigowo-Malanylem Road;Chesunut-Kapcherinyit Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,572,000.00 Soliat Feedback
Kap Zakayo- Ainamoi Polythecnic Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,307,200.00 Ainamoi Feedback
Tabrason-Kiptugumo Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 6,459,424.00 Soliat Feedback
Nyinyitiet- Chemorir Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 560,000.00 Ainamoi Feedback
Kaboykek cattle dip - Kimugul Road; Kimugul koi Barak Road; kapsiongori - Arap ngeny Road; jolydab academy - kaprero Road; Arap Chepsengeny - Chemaluk Road; Chemaluk - Cheptembe Road; Kap injelio - Kap George Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,443,664.00 Soliat Feedback
Kiburet- Nyinyitiet Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 420,000.00 Ainamoi Feedback
Seska- Arap Seronik -Arap Chepsegeny- Chemaluk Rad; Jolydab- Kap Rero Road; Chemaluk Church of Christ- Kapsegut Pry- Cheptembe Road; Kapkingok- Birirbei- Chepkoson Road; Koibarak-Kimgul Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,471,400.00 Soliat Feedback
Duka Moja- Kiparao Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,409,180.00 Kapkugerwet Feedback
Kurabei - Mogonjet ; Kurabei/Arap Ngeno - Chepkoson; Soliat Dispensary/boys -Chepkoson Road; Soliat Boys Sec School -Soliat AGC road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 7,529,400.00 Soliat Feedback
Sumeiyon- Chelogoi Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,038,000.00 Kapkugerwet Feedback
AGC Chesunet - Kapchesengeny Road; Motero pry - Kapkitandyus Road; Kapcherunyit - Kurabei Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,724,052.00 Soliat Feedback
Kapriwet- Arap Nyige To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,747,300.00 Kapsaos Feedback
Kapingok-Kapchepkaigat -Kurabei road; Arap Chebochok-Arap chepkoit road: Kapchelemei-Kongeren river-Salgaa road: Soliat Boys Sec School-Turguito bridge road: Kongeren pry – Mirmiro: Kapshongiroi - Arap Ngeny: Kaboykek cattle dip - Kapchesilim - Kapsigilai Road : Kaptelo – Chelogong Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,352,400.00 Soliat Feedback
Manyoror Sign Post- Manyoror Sec- Off Kapsaos Ainamoi Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,316,250.00 Kapsaos Feedback
Seska- Arap Seronik -Arap Chepsegeny- Chemaluk Rad; Jolydab- Kap Rero Road; Chemaluk Church of Christ- Kapsegut Pry- Cheptembe Road; Kapkingok- Birirbei- Chepkoson Road; Koibarak-Kimgul Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 3,211,800.00 Soliat Feedback
Torochgaa- Koigaron- Tegunot Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 2,393,784.00 Kapsaos Feedback
Kapnyakitari Centre - Kiptugumo Dispensary Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 5,893,600.00 Soliat Feedback
Kosisit Primary- Kap Abinwas- Arap Rugut To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,300,452.00 Kapsoit Feedback
Kaplengeny - Kiptugumo Road; Tabrasin - Kiptugumo dispensary Road; Kapneesoi - Highway - Moretik - Arap Tuei Road; Soliat Boys - Kongeren river- Kapchelemei Road; Kongeren pry - Mirmiro Road; Siriat – Kapsisirwo Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,384,000.00 Soliat Feedback
Off B1- Chepsoo Pry School Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 1,890,404.00 Kapsoit Feedback
Shauri Yako - Kapkenyelo - Kipcheiyet Road; Kapkara - Karap Cheruiyot Road; Kapchesengeny - Chepyegon - Kapchepchilat Road To improve road infrastructure and ensure effective drainage Public Works, Roads and Transport Completed 4,969,156.00 Soliat Feedback