2021/2022 FINANCIAL YEAR PROJECTS

Bureti Sub County

- All Projects-
Go back

Project Department Status Budget(Kshs) Ward
Proposed Culverts Installation To Bosuben Junction-Tanguret Road,Kipteran-Kapsinendet Church Of Christ Road,Kap Petero-Kapsimbiri Dip Road,Kapsimbor-Kap Mosonik Shops,Arokyet Tinga-Kap Cape Town Road Public Works, Roads and Transport On-Going 1,900,928.54 Cheplanget Feedback
Supply,delivery and installation of culverts at Chebinyiny-Kenene rd,Mobet-tabut rd,mobet-keregut road Public Works, Roads and Transport On-Going 1,847,972.80 Cheplanget Feedback
Routine Maintenance of Silva junction-Siongi-Kampala road Public Works, Roads and Transport On-Going 3,640,590.40 Tebesonik Feedback
Construction of Kelunet-Kapkimoro Road Public Works, Roads and Transport Completed 500,010.45 Tebesonik Feedback
Construction of Kipkoskei-Kapkolumbei Road, 0.5km, cheboin tbc-Kaprap joshua r 1.5km,arap koskei-Faith Church-Kapnyangai river-bot elijah corner tatu-Link Highway Road 2.7km Public Works, Roads and Transport Completed 1,193,841.00 Cheboin Feedback
Construction of Kenene Quarry- Kenene TBC Road 0.9km; Cheplanget Market Roads 0.3Km; Twoliot TBC- Kapsogeruk Bridge Road 1Km, Kaldit TBC- Matureti Road 1Km; Cheplanget Market- Kapsiongei Road 1.4Km Public Works, Roads and Transport Completed 937,092.08 Cheplanget Feedback
Construction of Arap Kesoro-Tamboiyot Box Culvert Road 0.6Km,; Kap Petero-Kap Simbirir Dip Road 0.6Km, Kapsimbirir-Kap Mosonik Shop Road 1.1Km, Arokyet Tinga- Kap Cape Town Road 1.1Km Public Works, Roads and Transport Completed 3,448,076.80 Cheplanget Feedback
Construction of Mombwo Pry- Sugutek TBC Road 0.8Km; Arap Kesembe- Caterpillar Road 2km; Bosuben Junction- Tanguret Road 1.3Km; Kipteran-Kapsinendet Church of Chridst Road 1.3Km Public Works, Roads and Transport Completed 1,670,678.40 Cheplanget Feedback
Construction of Off Chesingoro TBC-Kapsumet TBC-Chililis-Morit bridge Road Public Works, Roads and Transport Completed 3,287,129.12 Chemosot Feedback
Construction Of Kaprongori-Kaprote Roads2.3Km,Tulwet-Ngainet Road 1.7Km Public Works, Roads and Transport Completed 3,975,268.96 Kisiara Feedback
Construction of Chemeteget- Molyolok-Kimulwo Deliverance- Off C23 Roads; OFC Church- Shallai- Chelilis Primary School Road Public Works, Roads and Transport Completed 3,897,196.32 Chemosot Feedback
Construction Of Kaprongori-Kaprote Roads2.3Km,Tulwet-Ngainet Road 1.7Km Public Works, Roads and Transport Completed 2,730,644.64 Kisiara Feedback
Construction of Keregut-Taach Centre Road 1km,Tinga-Tulwap Kipsigis Road 0.3km,Misoi-Chebirribei-Aroron Road 0,85km,Mongoita-Chemamanik Road 0.4km,Sunset Junction-Chepkoiyo Road 1km, Kelelwa-Chepkoiyo Road 0.7km,Kasebet-Chepkembe Road 1km Public Works, Roads and Transport Completed 2,496,709.00 Kisiara Feedback
Shiners-Temuge r 0.4km, Kaptirbet-koros-ngesumin Road 2.5km, Kapkatet mortuary-Cementry Road 0.4km, Kapkatet Factory-Nganaset Road 0.6km, cherandas-sewerer Road 0.3km, kapkatet-AIC Holy Harvest church Road 0.5km,Kap mp-cherus tbc Road 0.6km, Off main Road-arap chepkwony Road 0.6km,off main Road-dcs residence Road 0.2, off main road kiko Road 0.2km matunda Road 0.2km, 954east-kipkosil pry sch Road 0.5km,mabwaita Aic -Catholic church Road 1km Public Works, Roads and Transport Completed 3,495,316.64 Kapkatet Feedback
Koiwa-Pefa church Road, chebagal tbc,ainapset river agc Road, Tendwet-Kaphilimon Road;Pefa Church-Cheptigit -Arap Maina Road, Kapkaren-Soet Road Public Works, Roads and Transport Completed 5,845,379.00 Litein Feedback
Chepkeikei Water Project Water, Environment, Energy and Natural Resources Completed 4,437,140.00 Soliat Feedback
Proposed Construction of Chesingoro- Lalagin Box Culvert Public Works, Roads and Transport Completed 1,402,532.80 Chemosot Feedback
Proposed Twin 900mm Cross Culverts to Cherara Bridge, Chebululu- Ng'erng'erwet Road and Kimugul- Ngainet TBC Road At Ngepchebyaat River Public Works, Roads and Transport Completed 2,834,996.18 Kisiara Feedback
Routine Maintenance of Chebitet-Kap Tebengwet road Public Works, Roads and Transport Completed 3,187,540.80 Kapkatet Feedback
Routine Maintenance of Reresik-Kiprichait-Roret boys-Chebululu-Tulwet-Ngainet bridge Public Works, Roads and Transport Completed 4,629,140.08 Kisiara Feedback
Routine Maintenance of Kapkarin-Chesoen TBC road Public Works, Roads and Transport Completed 3,469,031.04 Litein Feedback
Routine Maintenance of Ainapset A.I.C-kap Bomwo-Rungut primary-Chemsembe-Tenwet T.B.C road Public Works, Roads and Transport Completed 1,548,176.83 Litein Feedback
Routine Maintenance of Kibolgong-Tiriitab Eito road Public Works, Roads and Transport Completed 4,397,908.00 Tebesonik Feedback
Routine Maintenance of Kibaranji-Karapngerer road Public Works, Roads and Transport Completed 4,162,824.00 Tebesonik Feedback
Kaminjeiwa Education, Youth Affairs, Sports, Culture and Social Services Completed 4,099,400.00 Tebesonik Feedback
Construction of a pit latrine at Kusumek ECDE Centre Education, Youth Affairs, Sports, Culture and Social Services Completed 3,896,440.00 Chemosot Feedback
Construction of a pit latrine at Kamenjo ECDE Centre Education, Youth Affairs, Sports, Culture and Social Services Completed 3,598,436.00 Tebesonik Feedback
Construction of a 3 door pit latrine at Kaptirbet ECDE Centre Education, Youth Affairs, Sports, Culture and Social Services Completed 4,097,537.60 Kapkatet Feedback
Construction of a classroom at Kimugul ECDE Centre Education, Youth Affairs, Sports, Culture and Social Services Completed 4,495,710.85 Kapkatet Feedback
Construction of a classroom at Chebagal ECDE centre Education, Youth Affairs, Sports, Culture and Social Services Completed 4,491,520.00 Litein Feedback
Construction of a classroom at Nyambolosa ECDE centre Education, Youth Affairs, Sports, Culture and Social Services Completed 3,499,752.48 Litein Feedback
Construction of pit latrine at Kelunet ECDE Centre Education, Youth Affairs, Sports, Culture and Social Services Completed 3,097,880.00 Tebesonik Feedback