2022/2023 FINANCIAL YEAR PROJECTS

Bureti Sub County

- All Projects-
Go back

Project Department Status Budget(Kshs) Ward
Proposed Construction of Kaptebengwet- Cheptangulgei River Box Culvert Public Works, Roads and Transport On-Going 1,409,706.24 Kapkatet Feedback
Construction of Kaptirbet River (Semi Box Culvert (21m, 900MM) Public Works, Roads and Transport Completed 1,993,154.40 Kapkatet Feedback
Construction of Chesingei – Cheptalus Road 0.4km; Atebwo TBC – Koweek River Road 0.7km; Kwa Aurelius – Tuiyobei Kapstanley Road 1.5km Public Works, Roads and Transport Completed 1,959,472.00 Cheboin Feedback
Construction of Cllr Jane- Dip – Kimwogit Kongasis Road 1km; Cheptinet – Kapchebo Road 1.9km; Kaptangul – Kapcheluget Road 5.5km Public Works, Roads and Transport Completed 3,701,897.00 Cheboin Feedback
Construction of Kapdaut – Kiptewit Dispensary Road 1.5km; Chebaibai – Tetile Road1.5km; Kapkitende – Birirbei Road 0.5km Public Works, Roads and Transport Completed 3,999,158.00 Cheboin Feedback
Construction of Chematui – Bosco – Korongoi Girls Road 2.3km Public Works, Roads and Transport Completed 1,359,288.00 Cheboin Feedback
Construction of Kipwastuiyo-Asururiet Bridge Road 1.2Km, Lelach Junction-Lelach Girls Road 0.7Km, Joyland Academy-Chesanga Pry Shool Road 0.3Km, Asururiet Bridge- Masubeti Pry School Road 1.2Km, Kipwastuiyo Mkt- Kenene Quarry Road 2Km (Grading Only) Public Works, Roads and Transport Completed 6,222,555.00 Cheplanget Feedback
Construction of Mosore Dip- Kap Daktari Road 1.6Km; Sachangwan- Roret ICT Road 2Km; Tendwet- Arap Leitich Road 1.5Km Public Works, Roads and Transport Completed 1,517,289.28 Kisiara Feedback
Construction of Mosore Dip- Kap Daktari Road 1.6Km; Sachangwan- Roret ICT Road 2Km; Tendwet- Arap Leitich Road 1.5Km Public Works, Roads and Transport Completed 1,705,025.00 Kisiara Feedback
Routine Maintenance of Kabianga University- Chematich- Kaptirbet Road Public Works, Roads and Transport Completed 2,020,573.84 Kapkatet Feedback
Construction of Kap Johna-Cheribo Road 2Km; 954Mission-Arap Lele Road 1Km; Nyambolosa-Kipkurgat Road 0.6Km; Kipkuna- Chebwagan TBC Road 2Km; Lebekwet-Kolonget Road 0.7Km; Kap Bembe-Munywet Road 0.2Km Public Works, Roads and Transport Completed 1,387,763.68 Litein Feedback
Construction of Kaptibin- Kap Chief- Tabet Road 1.5Km, Barotion- Kiptongit- Kapkarin Road 3.2Km, Chebwagan AIC_ Kipkuna Road 1.5Km Public Works, Roads and Transport Completed 1,941,176.68 Litein Feedback
Kaptebengwet-Inat Road 1.9km,Chemobei-Kapjohnstone-Nyamanga Road 2km,Nairobi-Kaptebengwo Road 0.4km Public Works, Roads and Transport Completed 1,523,634.48 Tebesonik Feedback
Kaptebengwo- Innat Road 1.7Km, And Chemobei- Kap Johnstone-Nyammaganga Road 1.8Km, Nairobi- Kaptebengwet Road 0.4Km Public Works, Roads and Transport Completed 1,697,524.28 Tebesonik Feedback
Proposed Routine Maintenance of Ngoina Agc- Kipsamoi Cattle Dip Road Public Works, Roads and Transport Completed 3,727,312.56 Tebesonik Feedback
Proposed Routine Maintenance Cheptagum-Kibirech Road Public Works, Roads and Transport Completed 3,620,249.57 Tebesonik Feedback
Kap Joseph Maritm- Kap57-Kap George Mutai- Kipkeles Road Public Works, Roads and Transport Completed 1,700,246.80 Tebesonik Feedback