2017/2018 FINANCIAL YEAR PROJECTS

Bureti Sub County

- All Projects-
Go back

Project Department Status Budget(Kshs) Ward
Ngeny-green leaf academy Public Works, Roads and Transport Completed 7,155,866.00 Tebesonik Feedback
Kapkisiara junction- chesamisiet road Public Works, Roads and Transport Completed 3,912,518.00 Tebesonik Feedback
Cherote cheptagum pry kapelex kobologong Public Works, Roads and Transport Completed 2,128,175.00 Tebesonik Feedback
Nigeria - Kabusienduk rd Public Works, Roads and Transport Completed 4,221,640.00 Tebesonik Feedback
Kapkatet Hospital - Link cheplanget -Off mainroad Sosit Public Works, Roads and Transport Completed 3,979,443.80 Kapkatet Feedback
Town drainage culverts Public Works, Roads and Transport Completed 3,732,360.00 Litein Feedback
Construction of Kabartegan AIC- Kap Patrick Road Public Works, Roads and Transport Completed 2,777,453.00 Chemosot Feedback
Construction of Chebitet- Kaptumbo Road Public Works, Roads and Transport Completed 3,108,851.62 Kisiara Feedback
Construction of Kaptumo – chankelek Road Public Works, Roads and Transport Completed 524,041.60 Kisiara Feedback
Construction of Sikongo- Kondamet Road Public Works, Roads and Transport Completed 599,176.40 Kisiara Feedback
Kiptenden TBC- Kiptenden Pry sch road Public Works, Roads and Transport Completed 676,512.00 Litein Feedback
Chebwagan- Lebekwet- Kolonget Road Public Works, Roads and Transport Completed 3,896,846.00 Litein Feedback
Kiptuigo-koiyet rd Public Works, Roads and Transport Completed 1,643,870.80 Cheboin Feedback
Spencon- KapChebo School Road Public Works, Roads and Transport Completed 3,387,548.00 Cheboin Feedback
Ngororga-cheptigit sachangwan rd Public Works, Roads and Transport Completed 2,483,941.35 Cheboin Feedback
chakoror-chematui rd Public Works, Roads and Transport Completed 2,279,516.00 Cheboin Feedback
Off C23-chemosot- Chebulu TBC-Chereres - kaminjeiwet Road Public Works, Roads and Transport Completed 9,963,559.04 Cheboin Feedback
Chemosit - chebarema - kabitungu rd Public Works, Roads and Transport Completed 19,780,000.00 Chemosot Feedback
Awrorwet TBC- Bargiro Primary- Kiptyemat River Road Public Works, Roads and Transport Completed 420,000.00 Chemosot Feedback
Chebotawa- Getarwet- Samuget Road Public Works, Roads and Transport Completed 6,192,474.40 Chemosot Feedback
Kaptirbet-Kaptich-Kabianga University Campus rd Public Works, Roads and Transport Completed 357,375.20 Kapkatet Feedback
ainapkarik bridge-mabwaita TBC road Public Works, Roads and Transport Completed 740,875.00 Kapkatet Feedback
Kaproret-Rwandit AIC Church rd Public Works, Roads and Transport Completed 756,875.00 Kisiara Feedback
Chamamanik - kelelwa culvert installation Public Works, Roads and Transport Completed 3,802,524.00 Kisiara Feedback
Isacco-Lalagin Rd Public Works, Roads and Transport Completed 2,081,000.00 Litein Feedback
Kapkitony banda-kapsimet river rd Public Works, Roads and Transport Completed 3,858,915.00 Litein Feedback
Lalagin junction-Lalagin sec. rd Public Works, Roads and Transport Completed 1,600,800.00 Litein Feedback
Ngesumin girls - kipsamoi river ngeny pry junction- pry sch Public Works, Roads and Transport Completed 3,000,000.12 Litein Feedback